The Phase II project of Wuhan Metro Line 6 is 7.0km long, entirely underground, with 5 stations and an average station spacing of 1.4 km.
Our company provided communication system equipment and services for the public security communication system and passenger information system of the Phase II project. This includes the procurement and integration of equipment for the public security communication system, which comprises a video surveillance system, a wireless communication system for fire control, a computer network system, a power supply system, and grounding, as well as the supply of equipment and materials for the passenger information system, construction, optical cables, and cables. We also provided design liaison, factory manufacturing, factory acceptance, equipment supply, installation supervision, single-machine debugging, system joint debugging, trial operation, training, and other related services.
The project commenced on April 29,2020, completed quality acceptance on November 15,2021, and began trial operation on December 26,2021.
Due to its outstanding performance, the project was awarded the 'Wuhan Metro Group Co., Ltd. Wuhan Metro Line 6 Phase II Project Merit Unit' trophy and certificate of honor.

Project design liaison

Project completion quality acceptance
Merit unit honor